I guess it’s been a bit since I talked about the “barn” we’re building.
Over the next two weekends after the roof shingles were installed, I got the remaining sheathing installed on the barn:
And then came the air and water barrier installed over the next two weekends:
The next few weeks after that were involved with our annual pilgrimage to Florida and New Orleans.
Mid-September I build myself a workbench and started getting my tools moved from all the places I had them stored and started organizing.
We picked up the first door and installed it the next weekend.
And then this past weekend we picked up the French doors. That was a wee bit interesting getting it home. But in about 2 hours we got those installed. We also ordered the concrete fiber siding, which Lowe’s was supposed to deliver Monday morning.
Well, Monday morning came and went. And no delivery. They finally dropped off the siding around 3 PM.
I’ll get to starting installing that this coming weekend.
Until next time...